Client: DGW Group Pty Ltd
Project: St Rita’s College, Clayfield
Duration: July 2009 to January 2009
Project Value: $370,000
Project Details: Our contract was to undertake the site strip and bulk earthworks, demolition and piling contract. We have also removed asbestos from both internal and external buildings. This project is interesting due to its existing landscape with existing buildings being partially demolished and built over, the large amount of excavation for underground tanks. We also undertook the shoring piles and later in this contract we will have bored piers and a small asphalt patch job.
We are working hard at South Pine Sports Complex to finalise construction of the new soccer facilities. These facilities which include a High Performance Club House and a Local Club House facility along with 4 new soccer fields will provide a much welcome addition to the complex. We are sure that after the excitement of the World Cup Soccer recently held in Australia that soccer clubs will be receiving an influx of players.
28/09/2023